Report for July 2018

Report Date
July 2018

Project Start was approved by WIS at the meeting on 13/07/18. 

A small amount of Initiation work has since been undertaken.

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project status moved to Green now formal 'Start' approval granted by WIS.
Change Status
Activity
Approved budget
108.0 days
Activity this month
3.7 days
Activity this year
3.7 days
Activity to date
3.7 days
Estimate to complete current year
0.0 days
Estimate to complete future years
104.3 days

Project Info

Project
Estates Facilities Management (CAFM) Optimisation
Code
EST115
Programme
Estates Operations Optimisation (EOO)
Management Office
ISG PMO
Project Manager
Helen Lobb
Project Sponsor
Grant Ferguson
Current Stage
Plan
Status
In Progress
Project Classification
Transform
Start Date
01-Jun-2018
Planning Date
11-Oct-2019
Delivery Date
13-Mar-2020
Close Date
31-Mar-2020
Programme Priority
2
Overall Priority
Higher
Category
Discretionary

Documentation