Report for September 2019
- Report Date
- September 2019
Achievements Last Period
- Project Brief reviewed by Programme Manager
- Detailed cost estimates and 3-point estimate completed
- PIN/RFI WP delivery timeline agreed
- PIN/RFI draft and supplier response template completed. Reviewed by Procurement and key Estates stakeholders. Approved by Project Sponsor ready for release 1st October
- Business requirements (interviews) and current operating model details continue to be captured
- Business workshops scheduled and workshop planning commenced
- CAFM Programme high level plan/timeline produced
- CAFM Programme cost model framework commenced in line with proposed timeline (IS/Estates/Supplier and solution costs for Procurement and Implementation projects)
Issues / Outstanding
- Awaiting Estates Transformation Programme Change Manager return from annual leave/sick leave to review/finalise Project Brief and Programme timeline. Delay to End of Planning/WIS approval
- Continued 'activity' reporting discrepancies month to month (ASTA figures do not match separately tracked figures). ASTA totals reported each month.
- Revised resource requirements to be logged in ASTA following Project Brief sign off
Next Steps
- Review and sign off of Project Brief, Plan and Programme Timeline
- End of Planning submission to WIS
- Continue with capturing business requirements and detailed current operating model - complete interviews
- Plan and carry out workshops
- Enhance Programme cost model framework
- Await PIN responses
- Approved budget
- 108.0 days
- Activity this month
- 23.6 days
- Activity this year
- 50.4 days
- Activity to date
- 122.4 days
- Estimate to complete current year
- 45.6 days
- Estimate to complete future years
- 0.0 days