Report for August 2019

Report Date
August 2019

 

Achievements

  • Training - Training has now completed on Myproject. Sixty-six  users have been trained on Myproject and have entered  financial data and core data into the system. 
  • eFIN Integration build:  The E-Fin daily feed is now up and running.  Further changes/fixes  have been identified by the Business and these have now been developed ,tested and implemented in the Live environment successfully. These changes will filter the data that is being transferred across to only seven cost codes and balances prior to August 2005 will be set to August 2005.
  • Security Testing : Penetration testing -The penetration testing has been completed on the API and  on the server build. The pen test has identified areas  on the server and the API that  will  need to be updated to make them more secure.  These actions will be actioned by the responsible parties. 
  • Service Management: Regular meetings have now been set up with the supplier, Applications Management and Estates to review the open support calls and agree appropriate actions. This is progressing , the next steps will be to ensure that there is a robust process in place to support the service going forward.
  • Service Transition Management- Stage 2, 3 and 4 have been signed off by Estates and payments have been made to Polarisoft. Stage  5 is currently awaiting sign off by the business. 

Next Steps

  • Ensure all high/medium actions from the Penetration test are allocated to owners
  • Close down any issues on Jira related to technical development for EST103
  • Complete Stage Gate 5 for  Service Transition
  • Send out Closure Document

Issues

No issues currently

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
The RAG status for time is set to Amber as we are awaiting delivery of functionality from the supplier. This has come out of User Acceptance Testing- these are showstoppers which need to be retested
Change Status
Time
No Change
Cost
No Change
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Change Status has been set to Red as we are awaiting some showstoppers in terms of functionality from Polarisoft which was an outcome of testing
Activity
Approved budget
514.0 days
Activity this month
14.3 days
Activity this year
457.3 days
Activity to date
560.3 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Estates EPPM Implementation (EST103)
Code
EST103
Programme
Estates Capital System (EPPM)
Management Office
ISG PMO
Project Manager
Shirley Blyth
Project Sponsor
Jane Johnston
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
13-Jun-2017
Planning Date
15-Nov-2018
Delivery Date
13-Jun-2019
Close Date
15-Nov-2019
Programme Priority
2
Overall Priority
Highest
Category
Discretionary