Status GREEN: EST103 Estates Capital System Implementation - Initiation Activities Underway

Report Date
August 2017

Achievements

EST103:  Business engagement presentation for transition & implementation planning 16th Aug.

WIS approval received 25/08/17

Implementation Planning Underway

 

Next Steps

EST103:  Prepare Implementation Plan.  (Mid October 2017)

EST103:  Prepare Project Brief.  (Mid October 2017)

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Estates EPPM Implementation (EST103)
Code
EST103
Programme
Estates Capital System (EPPM)
Management Office
ISG PMO
Project Manager
Shirley Blyth
Project Sponsor
Jane Johnston
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
13-Jun-2017
Planning Date
15-Nov-2018
Delivery Date
13-Jun-2019
Close Date
15-Nov-2019
Programme Priority
2
Overall Priority
Highest
Category
Discretionary