Report for August

Report Date
August 2016

Achievements in Last Period

  • Business analysis: Space Mgmt complete and signed-off.
  • Business analysis: Maintenance Mgmt complete, and in final sign-off cycle.

Issues

  • No project sponsor.
  • Project is dependent upon the outputs of-outcomes from project COM025 (BI/MI architecture), and the emerging project COM029 (EDW build). Both of these projects are rpeorting delays against original milestones. .
  • The technical and development skills required for the project have been identified as a critical success factor. Discussions are on-going with the head of development services.
  • PM Resource constraint with EST080, leading to additional delays.

Next Steps

  • Complete business scoping.
  • Complete detailed business analysis.
  • Re-align project milestones.

The project is reporting RED as no sponsor is currently assigned, and the project lacks impetus within Estates compared to other, higher priority initiatives. 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
200.0 days
Activity this month
10.7 days
Activity this year
10.7 days
Activity to date
49.9 days
Estimate to complete current year
154.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Estates Strategic Reporting
Code
EST093
Programme
Estates General Programme (EST)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Karen Adamson
Current Stage
Close
Status
Closed
Start Date
17-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Sep-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary