Report for Apr 2016

Report Date
April 2016

Achievements in Last Period

Project initiated, 4 kick-off sessions held with Estates stakeholders.

Kick-off technical meeting held.

Issues

Change of Sponsor.

End of planning milestone has moved to 13/05.

Next Steps

Complete project planning phase

Commence analysis phase.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
200.0 days
Activity this month
8.1 days
Activity this year
10.5 days
Activity to date
10.5 days
Estimate to complete current year
66.6 days
Estimate to complete future years
125.6 days

Project Info

Project
Estates Strategic Reporting
Code
EST093
Programme
Estates General Programme (EST)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Karen Adamson
Current Stage
Close
Status
Closed
Start Date
17-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Sep-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary