Report for Mar 2016
- Report Date
- March 2016
Achievements in Last Period
- Project started, initial planning conducted.
Issues
- Availability of Sponsor.
- Outstanding request to move the planing date from 8th April to 22nd April.
Next Steps
- Complete project planning phase
Milestones
TBD
Start Date 09/03 (was 08/02)
Planning date 08/04 (was 25/03)
- Approved budget
- 200.0 days
- Activity this month
- 1.7 days
- Activity this year
- 2.3 days
- Activity to date
- 2.3 days
- Estimate to complete current year
- 74.2 days
- Estimate to complete future years
- 125.3 days