Report for Mar 2016

Report Date
March 2016

Achievements in Last Period

  • Project started, initial planning conducted. 

Issues

  • Availability of Sponsor.
  • Outstanding request to move the planing date from 8th April to 22nd April.  

Next Steps

  • Complete project planning phase

Milestones

TBD

Start Date 09/03 (was 08/02)

Planning date 08/04 (was 25/03)

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
200.0 days
Activity this month
1.7 days
Activity this year
2.3 days
Activity to date
2.3 days
Estimate to complete current year
74.2 days
Estimate to complete future years
125.3 days

Project Info

Project
Estates Strategic Reporting
Code
EST093
Programme
Estates General Programme (EST)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Karen Adamson
Current Stage
Close
Status
Closed
Start Date
17-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Sep-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary