Report for August 2017
- Report Date
- August 2017
Achievements in Last Period
- Initial Analysis refresh and initiation / induction sessions conducted.
- Re-planning underway. Project team reconvened, estimation workshop conducted.
- Business project team established.
Issues
- End-of re-planning milestone late, although analysis work is underway.
- Likely additional budget required.
Next Steps
- Reach end-of-planning milestone.
The project is reporting AMBER, until re-planning submitted and approved.
- Approved budget
- 200.0 days
- Activity this month
- 6.3 days
- Activity this year
- 6.3 days
- Activity to date
- 69.8 days
- Estimate to complete current year
- 44.6 days
- Estimate to complete future years
- 0.0 days