Report for June 2017

Report Date
June 2017

Achievements in Last Period

  • Project governance papers for reactivation submitted to WIS and approved.  
  • Meeting held with business leads Colin Pritchard, Richard Mann and commitment gained their involvement in BA refresh work.
  • Engagement of external MI/BI BA expertise in progress. We expect to make a decision this week.

Issues

  • None

Next Steps

  • Engage MI/BI Business analyst
  • Review / update Maintenance Mgmt, Space Business Analysis
  • Review brief / plans / estimates / risks / issues
  • Plan build / execution phases. 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
200.0 days
Activity this month
1.9 days
Activity this year
21.5 days
Activity to date
60.7 days
Estimate to complete current year
19.8 days
Estimate to complete future years
124.2 days

Project Info

Project
Estates Strategic Reporting
Code
EST093
Programme
Estates General Programme (EST)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Karen Adamson
Current Stage
Close
Status
Closed
Start Date
17-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Sep-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary