Report for May 2017
- Report Date
- May 2017
Achievements in Last Period
- Review meeting held 25/07. See https://www.projects.ed.ac.uk/unpublished/project/est093/meetings/project-review-meeting-0
- Karen Adamson has been appointed Project Sponsor
- Colin Pritchard, Richard Mann are business leads for maintenance mgmt, space respectively.
- The project will re-start by re-viewing an updating the business analysis. We will do this in conjunction with DTI project DTI019.
- The project will run in parallel with the project building EDW (DTI006) and as such will be an "early adopter" of EDW.
Issues
- None
Next Steps
- Formally re-start project
- Engage MI/BI Business analyst
- Review / update Maintenance Mgmt, Space Business Analysis
- Plan build / execution phases
The project is reporting GREEN.
- Approved budget
- 200.0 days
- Activity this month
- 1.5 days
- Activity this year
- 19.7 days
- Activity to date
- 58.9 days
- Estimate to complete current year
- 22.9 days
- Estimate to complete future years
- 123.0 days