Report for Oct 2016
- Report Date
- October 2016
Achievements in Last Period
- None.
Issues
- No project sponsor yet in place. There has been a lack on impetus in moving this project onto the next stage. Following recent discussions with Estates, it looks likely a sponsor will be appointed to give the project the direction required. A meeting has been organised to discuss this.
- Project is dependent upon the outputs of-outcomes from project COM025 (BI/MI architecture), and the emerging project COM029 (EDW build). Details of the inter dependencies are emerging.
- The technical and development skills required for the project have been identified as a critical success factor.
- Milestones yet to be adjusted, due to the delays in the appointment of a sponsor.
- PM Resource constraint with EST080, leading to additional delays.
Next Steps
- Confirm appointment of Sponsor.
- Re-boot (or suspend) project, Re-align project milestones.
- Plan design, development phases
- Commence design
The project will continue to report RED until such time as a sponsor is officially appointed.
- Approved budget
- 200.0 days
- Activity this month
- 1.4 days
- Activity this year
- 12.9 days
- Activity to date
- 52.0 days
- Estimate to complete current year
- 146.5 days
- Estimate to complete future years
- 0.0 days