Report for Feb 2016

Report Date
February 2016

Achievements in Last Period

Project Manager has been assigned

Issues

None

Next Steps

Complete project planning phase incoporating

  • project brief
  • project estimate
  • project plan

Milestones

Start Date 09/03 (was 08/02)

Planning date 08/04 (was 25/03)

These are due to the late start to the project, with a new PM coming on-board 01/02.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
200.0 days
Activity this month
1.0 day
Activity this year
1.0 day
Activity to date
1.0 day
Estimate to complete current year
74.0 days
Estimate to complete future years
125.0 days

Project Info

Project
Estates Strategic Reporting
Code
EST093
Programme
Estates General Programme (EST)
Management Office
ISG PMO
Project Manager
Chris Lawford
Project Sponsor
Karen Adamson
Current Stage
Close
Status
Closed
Start Date
17-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Sep-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary