Report for April 2016
- Report Date
- April 2016
Achievements in Last Period
Environment set-up in DEV still in progress (see issues).
EBIS on-line code deployed in DEV, waiting for environment set-up to be completed.
Issues
Issue with display of Estates Drawings. Uses a piece of third party software autoviz that dosnt work under CF11/ CentOS. As a consequence, project milestones have slipped a further week.
Parallel EBIS On-line development in progress (EST080). Will require careful co-ordination, and possible additional effort by third party integrator.
Next Steps
Complete environment builds (DEV / TEST / LIVE).
Complete DEV sign-off
Complete TEST sign-off.
Deploy to LIVE
- Approved budget
- 49.0 days
- Activity this month
- 8.6 days
- Activity this year
- 24.6 days
- Activity to date
- 24.6 days
- Estimate to complete current year
- 27.0 days
- Estimate to complete future years
- 0.0 days