Report for Feb 2016

Report Date
February 2016

Achievements in Last Period

  • Project Manager assigned Feb 01.
  • Project brief created and approved.
  • Dev Tech activities underway : Review TAD, environemnts build.     

Issues

  • There are a couple of key dependencies relating to the availability of EBIS On-line, which is needed exclusively for EST091 for a period of 5 weeks, from 18/03 onwards.  EST080 Parallel testing must complete by 18/03, and there is a possibiilty that a conflicting Archibus development may be required. the situation is benig monitored.  

Next Steps

  • Complete environment builds. 
  • Commence application migration onto CF11.

Milestones

26-Feb-2016End of Planning
18-Mar-2016Base environments built
01-Apr-2016Dev sign-off
08-Apr-2016Integration Sign-off
15-Apr-2016UAT Sign-off
22-Apr-2016Deployed to LIVE
29-Apr-2016Project Closed

 

 

  •  
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
49.0 days
Activity this month
8.0 days
Activity this year
8.0 days
Activity to date
8.0 days
Estimate to complete current year
42.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EBIS On-Line ColdFusion Upgrade
Code
EST091
Programme
Estates General Programme (EST)
Project Manager
Chris Lawford
Project Sponsor
Maureen Masson
Current Stage
Build
Status
In Progress
Start Date
03-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a