Report for Feb 2016
- Report Date
- February 2016
Achievements in Last Period
- Project Manager assigned Feb 01.
- Project brief created and approved.
- Dev Tech activities underway : Review TAD, environemnts build.
Issues
- There are a couple of key dependencies relating to the availability of EBIS On-line, which is needed exclusively for EST091 for a period of 5 weeks, from 18/03 onwards. EST080 Parallel testing must complete by 18/03, and there is a possibiilty that a conflicting Archibus development may be required. the situation is benig monitored.
Next Steps
- Complete environment builds.
- Commence application migration onto CF11.
Milestones
26-Feb-2016 | End of Planning |
18-Mar-2016 | Base environments built |
01-Apr-2016 | Dev sign-off |
08-Apr-2016 | Integration Sign-off |
15-Apr-2016 | UAT Sign-off |
22-Apr-2016 | Deployed to LIVE |
29-Apr-2016 | Project Closed |
- Approved budget
- 49.0 days
- Activity this month
- 8.0 days
- Activity this year
- 8.0 days
- Activity to date
- 8.0 days
- Estimate to complete current year
- 42.0 days
- Estimate to complete future years
- 0.0 days