March 2016
- Report Date
- March 2016
Achievements in Last Period
- Attended first meeting with PWC to review the usage of the existing systems with regards to Capital Planning. Attended meeting with Graham Bell, Lee Hamill
- Have replanned project based on known PWC schedule
- Review PWC Capital Plan System System Development Report - 20/04/16
- Complete Review - 20/05/16
- Project Closure - 27/05/16
Issues
- Requirement now to consider if this project should remain open, now that activities are being led and coodinated by PWC
Next Steps
- Continue to participate in the PWC meetings
- Confirm if project should continue in its current format
The poroject manager has assigned a RAG status of Amber, whilst seeking clarity regarding the direction of the project
- Approved budget
- 15.0 days
- Activity this month
- 0.5 days
- Activity this year
- 6.0 days
- Activity to date
- 6.0 days
- Estimate to complete current year
- 9.0 days
- Estimate to complete future years
- 0.0 days