October 2015
- Report Date
- October 2015
Achievements in Last Period
- The two modules Capitial Budgeting and Project Management have been installed on both the Development and Test environments
- 2-day training workshop has been held
Issues
- Project sponsor unable to attend training workshop
Next Steps
- Project team to commence product evaluation
- Approved budget
- 15.0 days
- Activity this month
- 1.0 day
- Activity this year
- 1.0 day
- Activity to date
- 1.0 day
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 0.0 days