October 2015

Report Date
October 2015

Achievements in Last Period

  • The two modules Capitial Budgeting and Project Management have been installed on both the Development and Test environments
  • 2-day training workshop has been held

Issues

  • Project sponsor unable to attend training workshop

 

Next Steps

  • Project team to commence product evaluation
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
15.0 days
Activity this month
1.0 day
Activity this year
1.0 day
Activity to date
1.0 day
Estimate to complete current year
14.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Capital Budgeting Evaluation
Code
EST088
Programme
Estates General Programme (EST)
Project Manager
Andrew Stewart
Project Sponsor
Maureen Masson
Current Stage
Close
Status
Closed
Start Date
27-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jul-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation