February//March Update
- Report Date
- February 2015
Achievements in Last Period
- Migrated live Webcentral application server on 4th February
- The Deployment sign-off was completed on 26th February
- Approval to close the project was agreed on 4th March
Issues
- Project closure was delayed at the request of production to allow additional running time in new infrastructure. This delay was due to a tomcat crash shortly after migration, which after investigation could not be attributed to EST082.
Next Steps
- Formally close project
- Approved budget
- 17.0 days
- Activity this month
- 2.5 days
- Activity this year
- 17.0 days
- Activity to date
- 17.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days