October 2014
- Report Date
- October 2014
Achievement in Last Period
- Approval to commence the project was granted after the assignment of Mark Lang as project manager
- The planning phase of the project has now commenced
Issues
- Whilst there are no issues to report, it should be noted that this project is dependent on the project INF106 - New Application Tier Replacement, which is currently building the necessary infrastructure
Next Steps
- Complete and confirm the project brief with the project team and the project sponsor
- Approved budget
- 40.0 days
- Activity this month
- 0.3 days
- Activity this year
- 0.3 days
- Activity to date
- 0.3 days
- Estimate to complete current year
- 40.0 days
- Estimate to complete future years
- 0.0 days