w/c 6th June 2016 | Andrew Stewart | 07-Jun-2016 | |
w/c 30th May 2016 | Andrew Stewart | 07-Jun-2016 | |
w/c 23/05/16 |
|
Andrew Stewart | 27-May-2016 |
Mobile delivery due on 17-Nov (was 16 Oct), now 27 Nov... |
27-Nov /30-Nov Received but Dev failed, Test deployed ok JIRA EST080-79 raised Martin available 3-4th Dec for testing 24-Nov Martin alerted us to our choices for the mobile delivery delivery Wed morning for the deployment then Thursday between 10 and 12 and/or 13:30 and 17:00. Riky not available this week, will verify if Emilio available for Wed Morning 23-Nov |
Anne Mathison | 19-Nov-2015 |
College of Science and Engineering |
Feedback from Science and Engineering after demo 'After several years of faithful service the EBIS fault reporting system is about to be retired. A younger, smarter system is about to be launched . The new system will be web based and should provide a better system in terms of ease of reporting with more drop down options than ever before. |
Anne Mathison | 14-Oct-2015 |
New proposals received from Mass |
Received Fri 18-Sept, As per you detailed discussions with Martin Matt, please find attached our proposal for changes requested to ARCHIBUS to include: |
Anne Mathison | 21-Sep-2015 |
w/c 6th July 2015 |
|
Andrew Stewart | 07-Jul-2015 |
w/c 29th May 2015 |
|
Andrew Stewart | 08-Jul-2015 |
May update for 26th May Meeting Amber |
Unexpected system issues have been encountered after the upgrade to 21.3. Our service supplier Mass are scheduled to be on-site 26th May to further investigate, as they cannot re-create them |
Anne Mathison | 25-May-2015 |
w/c 11/05/15 |
|
Andrew Stewart | 13-May-2015 |
w/c 04/05/15 |
|
Andrew Stewart | 04-May-2015 |
Archibus upgrade |
EST086 Archibus Upgrade Dev 23-Apr
Test 24-Apr
|
Anne Mathison | 22-Apr-2015 |
EST080 Governance |
Geoff discussed Governance with David and Colin on Friday and agreed Colin, David, Maureen and Geoff will have monthly meetings. Rachel is arranging the meetings with them all. Geoff did not want to come to our weekly meetings, but likes the minutes and documents etc that we do for Estates
|
Anne Mathison | 10-Nov-2014 |
Unidesk versus Archibus Decision |
Alex, With reference to your comments. The decision to utilise the Archibus based application was arrived for a number of reasons; The strategic decision has been taken within Estates and Buildings that Archibus is the solution to assist mange the Estate related property |
Anne Mathison | 29-Oct-2014 |
Project Title change |
The project title will be changed from
Agreed at with Project Sponsor and Programme Manager at Brief Review Meeting 9-Sep-2014 Project Sponsor said this project will have a programme priority of 3. |
Anne Mathison | 10-Sep-2014 |
Info from July report to consider in Brief |
Plan Project scheduled to - commence in August 2014 - initial planning phase scheduled to be completed in September 2014 - delivery date scheduled for December 2014 Dependencies - will require a large commitment from Estates and Buildings business owner throughout all stages of the project - will require significant input from an IS Applications business analysis in determining the business requirements |
Anne Mathison | 03-Sep-2014 |