Achievements in Last Period

  • Stakeholder meeting held to review project objectives
  • Project brief prepared and subsequently approved by project team on 8th November and submitted to WIS for approval 

Issues

  •  None

 Next Steps

  • Agree planning for the Technical Investigation and Recommendation milestones. Once that is completed the remaining milestones and project scheduling will be agreed
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
25.0 days
Activity this month
1.0 day
Activity this year
1.0 day
Activity to date
1.0 day
Estimate to complete current year
25.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Energy Recording Systems Upgrade
Code
EST072
Programme
Estates General Programme (EST)
Project Manager
Anne Mathison
Project Sponsor
Geoffrey Turnbull
Current Stage
Close
Status
Closed
Start Date
11-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Jun-2013
Programme Priority
5
Overall Priority
Normal
Category