Breakdown Notes of Initial Requirements

Initial Requirements

  • Audit of existing server
  • Confirm what has to be moved
  • Determine required infrastructure and costs, suspect infrastructure at KB and AT
  • Confirm proposed solution with supplier
  • Build new environment
  • Data migration and Test
  • Requirement to ascertain long term support
  • Establish links with Estates and Building external suppliers

Project Info

Project
Energy Recording Systems Upgrade
Code
EST072
Programme
Estates General Programme (EST)
Project Manager
Anne Mathison
Project Sponsor
Geoffrey Turnbull
Current Stage
Close
Status
Closed
Start Date
11-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Jun-2013
Programme Priority
5
Overall Priority
Normal
Category
Compliance