December 2019 report
- Report Date
- December 2019
- Achievements in Last Period
-
Project brief drafted and signed off
-
Student recruitment completed and induction undertaken
-
Tasks assigned and project team assembled
-
Initial identification of sensor devices completed
-
Prototype sensor rig specified
Issues/Risks
- The project deadlines cannot be met due to the volume or work and/or lack of skilled or available resources that need to be assigned
- Due to insufficient support from third-party teams, there is a risk this may impact on the work that can be achieved by the core project team, which would result in delays to the project milestones
- Due to insufficient funding beyond the 60 days allocated from the ITI Enterprise Services Section project budget, there is a risk that no additional budget will be found which could result in the project not being able to complete.
- Estates are unable to provide a control interface to the air handling units and chiller controls
- The control of the temperature set point and air handling fan speed fails resulting in datacentre cooling failure
Next Steps
-
Prototype sensor rig components procured
-
Prototype sensor rig build
- Approved budget
- 60.0 days
- Activity this month
- 2.0 days
- Activity this year
- 2.0 days
- Activity to date
- 2.0 days
- Estimate to complete current year
- 58.0 days
- Estimate to complete future years
- 0.0 days