Report for September 2019

Report Date
September 2019
Project Withdrawn
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
Suspended
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Datacentre network implications resulting from Network deployment
Code
ENT210
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Graeme Wood
Current Stage
Initiate
Status
Withdrawn
Project Classification
Transform
Start Date
07-Oct-2019
Planning Date
25-Oct-2019
Delivery Date
05-Jun-2020
Close Date
03-Jul-2020
Overall Priority
Normal
Category
Compliance

Documentation

Not available.