Report for January 2020

Report Date
January 2020

Report Dated January 2020 

Achievements in Last Period

  • Project initiated

  • Project brief drafted and circulated

Issues/Risks
  • None
Next Steps 
  • Sign off Project Brief

  • Complete end of planning

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project RAG Status is GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
System Emails & Staffmail Decommissioning
Code
ENT208
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Graeme Wood
Current Stage
Initiate
Status
In Progress
Project Classification
Transform
Start Date
14-Jan-2020
Planning Date
07-Feb-2020
Delivery Date
03-Aug-2020
Close Date
24-Aug-2020
Programme Priority
3
Overall Priority
Normal
Category
Compliance

Documentation

Not available.