System Emails & Staffmail Decommissioning - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2020 GREEN 0.0 days 0.0 days 0.0
Content
Status
In Progress
Current Stage
Initiate
Start Date
Tuesday, 14 January 2020
Planning Date
Friday, 7 February 2020
Delivery Date
Monday, 3 August 2020
Close Date
Monday, 24 August 2020
Project information
Project Code
ENT208
Programme
ITI - Enterprise Services (ENT)
Session
20/21
19/20
Organisational Unit
IS IT Infrastructure
Project Management Office (if relevant)
ISG PMO
Responsibility
IT Infrastructure
Project Category
Compliance
Project Classification
Transform
Project Type
Implementation
Project Size
Medium
Project Complexity
Standard
Funding Source
ITI Core
Programme Priority
3
Overall Priority
Normal
Student Impact
Project deliverables will have no impact on students