Report for December 2019
- Report Date
- December 2019
Achievements in Last Period
-
Email Provisioner live testing incomplete causing removal of Applicant AD changes from go live deployment
-
Project Board approval of revised go live date and scope of deployment
-
New Authentication pages deployed on 18th November
-
Further communications on live deployment dates completed
-
Further engagement with stakeholders completed
-
Change to go to GoCAB approved
Issues/Risks
- Email Provisioner testing
Next Steps
-
Plan and implement remaining testing of Email Provisioner
-
Project Board approval for go live deployment of remaining functionality
-
Further communications to be scheduled
-
plan project close process and closure report
-
Project board approval for close
- Approved budget
- 400.0 days
- Activity this month
- 5.0 days
- Activity this year
- 22.0 days
- Activity to date
- 117.5 days
- Estimate to complete current year
- 78.0 days
- Estimate to complete future years
- 0.0 days