Report for May 2019

Report Date
May 2019
Testing almost complete; 
Achievements in Last Period
  • User groups and access policies completed
  • ENT based testing completed
  • Technical Management testing complete
  • Integration with Central Logging (ELK) completed ahead of schedule
Risks/Issues
  • No issues at present
Next Steps
  • Confirm Development Technology testing complete
  • Complete documentation
  • Announce service
Milestones                                                                            
Target Date Milestone Phase Complete
22/01/2019 Initial review of scope, requirements and timeline Initiate Yes
15/02/2019 Project brief  and project plan prepared Plan Yes
01/03/2019 Project brief and plan approved Plan Yes
01/03/2019 End of planning Plan Yes
15/03/2019 Overall Remote Desktop Gateway server and client installation process designed Design Yes
22/03/2019 Gateway user and server groups, VLANs and firewall configurations defined Design Yes
29/03/2019 Microsoft’s Remote Desktop Gateway installed on Windows management servers at JCMB and Appleton Tower Build Yes
12/04/2019 Windows firewalls configured for gateway access Build Yes
26/04/2019 Network firewalls configured for gateway access Build Yes
30/04/2019

Administrator groups in Active Directory authorised as gateway users

Build Yes
03/05/2019

Access policies defined in Active Directory for gateway

Build Yes
10/05/2019

Access to specific server groups by administrators' groups assigned

Build Yes
14/06/2019 Gateway access tested and proved from external clients Integrate Yes
07/06/2019 Process documentation completed and available on ENT wiki Deliver No
21/06/2019 Administrators trained on use of remote gateway Deliver No
01/07/2019 Remote gateway logs integrated into ELK central logging system Deliver Yes
02/07/2019 New remote gateway process presented at ENT monthly team meeting Deliver No
08/07/2019 Remote Gateway in production Deliver No
19/07/2019 Project closed Closure No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
48.0 days
Activity this month
4.0 days
Activity this year
24.0 days
Activity to date
24.0 days
Estimate to complete current year
10.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Remote Windows Server Management Solution
Code
ENT040
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
Graeme Wood
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
28-Jan-2019
Planning Date
01-Mar-2019
Delivery Date
08-Jul-2019
Close Date
31-Jul-2019
Overall Priority
Higher
Category
Discretionary

Documentation