ICED - Report for December 2019

Report Date
December 2019
Project Status
RAG Status
Overall
RED
RAG Commentary
Funding that came through cannot be paid to any institution outside of the US. This project will need to be paused until UK funding is available (no timeline available).
Change Status
Overall
Significant
Has formal escalation taken place?
Yes
Escalated to
Director of EDINA
Change Commentary
Due to lack of funding, timelines for this project are uncertain. Discussed with Director of EDINA.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ICED
Code
EDIP0167
Programme
EDINA 19/20
Management Office
ISG PMO
Project Manager
Ingrid Earp
Project Sponsor
Janet Roberts
Current Stage
Plan
Status
In Progress
Project Classification
Transform
Start Date
24-May-2019
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal

Documentation

Not available.