Report for January
- Report Date
- January 2013
Achievements in Last Period
- Enhancements list provided by ECA was assessed by ECA representatives and Development Team (will be used as requirements)
- Design and build work has commenced on enhancements
- Resources secured to deli
Issues
- Some clarifications on requirement have been raised as part of the design
Next Steps
- Review and sign off Design
- Complete build work
- Agree milestones and testing schedule (draft milestones below)
Milestones
| Target date | Title |
|---|---|
| 15-Feb-2013 | Requirements Sign Off |
| 26-Feb-2013 | Design Review |
| 06-Mar-2013 | Build Review |
| 21-Mar-2013 | Acceptance Test Sign Off |
| 25-Mar-2013 | Go Live |
| 01-Apr-2013 | Deployment Sign Off |
| 19-Apr-2013 | Close |
- Approved budget
- 45.0 days
- Activity this month
- 17.6 days
- Activity this year
- 24.9 days
- Activity to date
- 24.9 days
- Estimate to complete current year
- 21.0 days
- Estimate to complete future years
- 0.0 days