Report for January

Report Date
January 2013

Achievements in Last Period

  • Enhancements list provided by ECA was assessed by ECA representatives and Development Team (will be used as requirements)
  • Design and build work has commenced on enhancements
  • Resources secured to deli

Issues

  • Some clarifications on requirement have been raised as part of the design

Next Steps

  • Review and sign off Design
  • Complete build work
  • Agree milestones and testing schedule (draft milestones below)

Milestones

 

Target dateTitle
15-Feb-2013Requirements Sign Off
26-Feb-2013Design Review
06-Mar-2013Build Review
21-Mar-2013Acceptance Test Sign Off
25-Mar-2013Go Live
01-Apr-2013Deployment Sign Off
19-Apr-2013Close

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
45.0 days
Activity this month
17.6 days
Activity this year
24.9 days
Activity to date
24.9 days
Estimate to complete current year
21.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ECA Exam Board Enhancements
Code
ECA006
Programme
Z. ECA Portal and LMS (ECA) (closed 2012/13)
Project Manager
Craig Middlemass
Project Sponsor
Jared Taylor
Current Stage
Close
Status
Closed
Start Date
17-Dec-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2013
Programme Priority
2
Overall Priority
Normal
Category
Discretionary