Report for April
- Report Date
- April 2013
Achievements in Last Period
- The Business Requirements has been signed off
- The Design is ready for sign off in early May
- Build of Dev environment is almost complete
Issues
- The timing for the go live may need to move given the availability of staff and the need to avoid infrastructure moves while exam boards are still on (last board 24 June)
Next Steps
- Sign off the system design
- Complete Peer Testing
- Handover to ECA for User Acceptance Testing
Milestones
Target date | Title |
---|---|
25-Sep-2012 | Resume Project Work - complete |
19-Oct-2012 | Estimates from Dev Team and Dev Tech - complete |
05-Apr-2013 | Business Requirements Sign Off - complete |
06-May-2013 | System Design Sign Off |
17-May-2013 | Peer Test Sign Off |
03-Jun-2013 | User Acceptance Test Sign Off |
17-Jun-2013 | Deploy to Live |
24-Jun-2013 | Deployment Sign Off Review |
28-Jun-2013 | Closure |
- Approved budget
- 72.0 days
- Activity this month
- 11.0 days
- Activity this year
- 29.7 days
- Activity to date
- 45.0 days
- Estimate to complete current year
- 27.9 days
- Estimate to complete future years
- 0.0 days