Report for March
- Report Date
- March 2013
Achievements in Last Period
- The requirements and design work have both commenced
Issues
- Priority has been given to exam boards enhancements as such no progress has been made on this project
- A slight delay to some of the requirements and design sign off following overrun on ECA006 which is using the same people
Next Steps
- Complete Business Requirements and Sign Off
- Complete Design and Sign Off
Milestones
25-Sep-2012 | Resume Project Work - Complete |
19-Oct-2012 | Estimates from Dev Team and Dev Tech - Complete |
05-Apr-2013 | Business Requirements Sign Off |
12-Apr-2013 | System Design Sign Off |
24-Apr-2013 | Peer Test Sign Off |
21-May-2013 | User Acceptance Test Sign Off |
17-Jun-2013 | Deploy to Live |
24-Jun-2013 | Deployment Sign Off Review |
28-Jun-2013 | Closure |
- Approved budget
- 72.0 days
- Activity this month
- 6.3 days
- Activity this year
- 16.2 days
- Activity to date
- 31.4 days
- Estimate to complete current year
- 40.5 days
- Estimate to complete future years
- 0.0 days