Report for February

Report Date
February 2013

Achievements in Last Period

  • Milestones has been replanned but rejected by WIS need to re
  • No work has progressed other than finalising some of the Development Technology build for the infrastructure that the migration portal will reside on

Issues

  • Priority has been given to exam boards enhancements as such no progress has been made on this project

Next Steps

  • Complete Business Requirements and Sign Off
  • Re-submit milestones for WIS approval

Milestones

 

25-Sep-2012Resume Project Work - Complete
19-Oct-2012Estimates from Dev Team and Dev Tech - Complete
11-Mar-2013Business Requirements Sign Off
22-Mar-2013System Design Sign Off
24-Apr-2013Peer Test Sign Off
21-May-2013User Acceptance Test Sign Off
17-Jun-2013Deploy to Live
24-Jun-2013Deployment Sign Off Review
28-Jun-2013Closure

 

Project Status
Activity
Approved budget
72.0 days
Activity this month
0.8 days
Activity this year
9.9 days
Activity to date
25.1 days
Estimate to complete current year
47.3 days
Estimate to complete future years
0.0 days

Project Info

Project
ECA Portal Infrastrucuture
Code
ECA001
Programme
Z. ECA Portal and LMS (ECA) (closed 2012/13)
Project Manager
Craig Middlemass
Project Sponsor
Jared Taylor
Current Stage
Close
Status
Closed
Start Date
20-Oct-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Aug-2013