Report for February
- Report Date
- February 2013
Achievements in Last Period
- Milestones has been replanned but rejected by WIS need to re
- No work has progressed other than finalising some of the Development Technology build for the infrastructure that the migration portal will reside on
Issues
- Priority has been given to exam boards enhancements as such no progress has been made on this project
Next Steps
- Complete Business Requirements and Sign Off
- Re-submit milestones for WIS approval
Milestones
25-Sep-2012 | Resume Project Work - Complete |
19-Oct-2012 | Estimates from Dev Team and Dev Tech - Complete |
11-Mar-2013 | Business Requirements Sign Off |
22-Mar-2013 | System Design Sign Off |
24-Apr-2013 | Peer Test Sign Off |
21-May-2013 | User Acceptance Test Sign Off |
17-Jun-2013 | Deploy to Live |
24-Jun-2013 | Deployment Sign Off Review |
28-Jun-2013 | Closure |
- Approved budget
- 72.0 days
- Activity this month
- 0.8 days
- Activity this year
- 9.9 days
- Activity to date
- 25.1 days
- Estimate to complete current year
- 47.3 days
- Estimate to complete future years
- 0.0 days