Report for January
- Report Date
- January 2013
Achievements in Last Period
- Project has been submitted for suspension but reject by WIS
- No work has progressed other than finalising some of the Development Technology build for the infrastructure that the migration portal will reside on
Issues
- Priority has been given to exam boards enhancements as such no progress has been made on this project
Next Steps
- Restart development once exam boards enhancements (ECA006) complete
Milestones
Target date | Title |
---|---|
25-Sep-2012 | Resume Project Work - Complete |
19-Oct-2012 | Estimates from Dev Team and Dev Tech - Complete |
19-Dec-2012 | Business Requirements Sign Off - Replan |
30-Jan-2013 | System Design Sign Off- Replan |
27-Feb-2013 | Peer Test Sign Off- Replan |
29-Mar-2013 | User Acceptance Test Sign Off- Replan |
03-Apr-2013 | Deploy to Live- Replan |
17-Apr-2013 | Deployment Sign Off Review- Replan |
24-Apr-2013 | Closure- Replan |
- Approved budget
- 72.0 days
- Activity this month
- 0.2 days
- Activity this year
- 9.1 days
- Activity to date
- 24.4 days
- Estimate to complete current year
- 48.5 days
- Estimate to complete future years
- 0.0 days