Report for November
- Report Date
- November 2012
Achievements in Last Period
- Bookings had been secured for completing the work based on estimates to complete the project
- A re-prioritisation of the programme will mean that this project will be suspended until the exam board enhancements can be completed
Issues
- Priority has been given to exam boards enhancements as such this project will be suspended
Next Steps
- Submit suspension for project and pick up once exam boards complete
Target date | Title |
---|---|
19-Dec-2012 | Business Requirements Sign Off |
30-Jan-2013 | System Design Sign Off |
27-Feb-2013 | Peer Test Sign Off |
29-Mar-2013 | User Acceptance Test Sign Off |
03-Apr-2013 | Deploy to Live |
17-Apr-2013 | Deployment Sign Off Review |
24-Apr-2013 | Closure |
- Approved budget
- 72.0 days
- Activity this month
- 2.9 days
- Activity this year
- 8.6 days
- Activity to date
- 23.9 days
- Estimate to complete current year
- 49.1 days
- Estimate to complete future years
- 0.0 days