Report for October 2012
- Report Date
- October 2012
Achievements in Last Period
- Agreement was reached on the architecture to use (SQL Server and Cold Fusion on a window machine)
- Estimates completed for work on the basis of moving to the new architecture
- Build has commenced on the architecture that the ECA portal will migrate to
Issues
- Dev Team are unavailble to commence work until January due to other priorities
Next Steps
- Submit the following milestones and changes to WIS for validation
- Submit budget changes for validation by WIS
Target date | Title |
---|---|
19-Dec-2012 | Business Requirements Sign Off |
30-Jan-2013 | System Design Sign Off |
27-Feb-2013 | Peer Test Sign Off |
29-Mar-2013 | User Acceptance Test Sign Off |
03-Apr-2013 | Deploy to Live |
17-Apr-2013 | Deployment Sign Off Review |
24-Apr-2013 | Closure |
- Approved budget
- 50.0 days
- Activity this month
- 6.0 days
- Activity this year
- 6.0 days
- Activity to date
- 21.0 days
- Estimate to complete current year
- 44.0 days
- Estimate to complete future years
- 0.0 days