Report for October 2012

Report Date
October 2012

Achievements in Last Period

  • Agreement was reached on the architecture to use (SQL Server and Cold Fusion on a window machine)
  • Estimates completed for work on the basis of moving to the new architecture
  • Build has commenced on the architecture that the ECA portal will migrate to

Issues

  • Dev Team are unavailble to commence work until January due to other priorities

Next Steps

  • Submit the following milestones and changes to WIS for validation
  • Submit budget changes for validation by WIS

 

Target dateTitle
19-Dec-2012Business Requirements Sign Off
30-Jan-2013System Design Sign Off
27-Feb-2013Peer Test Sign Off
29-Mar-2013User Acceptance Test Sign Off
03-Apr-2013Deploy to Live
17-Apr-2013Deployment Sign Off Review
24-Apr-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
6.0 days
Activity this year
6.0 days
Activity to date
21.0 days
Estimate to complete current year
44.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ECA Portal Infrastrucuture
Code
ECA001
Programme
Z. ECA Portal and LMS (ECA) (closed 2012/13)
Project Manager
Craig Middlemass
Project Sponsor
Jared Taylor
Current Stage
Close
Status
Closed
Start Date
20-Oct-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Aug-2013