Report for September 2012

Report Date
September 2012

Achievements in Last Period

  • Project Prioritised as Top Project in the ECA progamme with an ideal delivery date in December 2012

Issues

  • Dev Team are unavailble to commence work until October due to other priorities
  • Need to make a final decision on the Infrastrucutre to opt (i.e. Oracle vs MS Sql Server)

Next Steps

  • Re-estimate the remaining work and transfer budget from the ECA 2012/13 budget
  • Make final decision on which was to take the infrastructure
  • WIS to agree budget increase for migration work

 

Target dateTitle
25-Sep-2012Resume Project Work

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
15.3 days
Activity this month
0.2 days
Activity this year
0.2 days
Activity to date
15.5 days
Estimate to complete current year
56.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ECA Portal Infrastrucuture
Code
ECA001
Programme
Z. ECA Portal and LMS (ECA) (closed 2012/13)
Project Manager
Craig Middlemass
Project Sponsor
Jared Taylor
Current Stage
Close
Status
Closed
Start Date
20-Oct-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Aug-2013