Report for September 2012
- Report Date
- September 2012
Achievements in Last Period
- Project Prioritised as Top Project in the ECA progamme with an ideal delivery date in December 2012
Issues
- Dev Team are unavailble to commence work until October due to other priorities
- Need to make a final decision on the Infrastrucutre to opt (i.e. Oracle vs MS Sql Server)
Next Steps
- Re-estimate the remaining work and transfer budget from the ECA 2012/13 budget
- Make final decision on which was to take the infrastructure
- WIS to agree budget increase for migration work
Target date | Title |
---|---|
25-Sep-2012 | Resume Project Work |
- Approved budget
- 15.3 days
- Activity this month
- 0.2 days
- Activity this year
- 0.2 days
- Activity to date
- 15.5 days
- Estimate to complete current year
- 56.0 days
- Estimate to complete future years
- 0.0 days