Report for August 2012

Report Date
August 2012

Achievements in Last Period

  • None - project suspended

Issues

  • The project is due to recommence, however, this work needs to be prioritised in line with the new work for 2013/14
  • Dev Team are unavailble to commence work until October due to other priorities

Next Steps

  • Prioritise project against other 2013/14 projects for ECA
  • Re-estimate the remaining work and transfer budget from the ECA 2012/13 budget
  • Restart development of the UoE Environment

 

 

Target dateTitle
03-Aug-2012Resume Project Work

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
15.3 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
15.3 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ECA Portal Infrastrucuture
Code
ECA001
Programme
Z. ECA Portal and LMS (ECA) (closed 2012/13)
Project Manager
Craig Middlemass
Project Sponsor
Jared Taylor
Current Stage
Close
Status
Closed
Start Date
20-Oct-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Aug-2013