Report for June

Report Date
June 2013

Achievements in Last Period

  • Sign Off User Acceptance Testing
  • Deploy to Live in early July

Issues

  • Due to annual leave constraints the go live has been brought forward

Next Steps

  • Handover to support and complete deployment checklist

Milestones

Target dateTitle
25-Sep-2012Resume Project Work
19-Oct-2012Estimates from Dev Team and Dev Tech
05-Apr-2013Business Requirements Sign Off
06-May-2013System Design Sign Off
24-May-2013Peer Test Sign Off
04-Jul-2013User Acceptance Test Sign Off
08-Jul-2013Deploy to Live
15-Jul-2013Deployment Sign Off Review
17-Jul-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
61.0 days
Activity this month
19.0 days
Activity this year
49.0 days
Activity to date
64.0 days
Estimate to complete current year
12.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ECA Portal Infrastrucuture
Code
ECA001
Programme
Z. ECA Portal and LMS (ECA) (closed 2012/13)
Project Manager
Craig Middlemass
Project Sponsor
Jared Taylor
Current Stage
Close
Status
Closed
Start Date
20-Oct-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Aug-2013