Report for December 2019

Report Date
December 2019

 

David and Graham will work on and present all documentation to the Desktop CAB in October for final approvals.

Director has requested prioritised action for this project after discussions with the project sponsor.

 

 

Achievements in Last Period

  • David and Graham to detail the Change Management Process for handling standard, minor and major changes - done
  • David and Graham to draft scenario for dealing with N-2 devices that drop from support : keep on jamf holding area/remove completely - done

Issues and Risks

  • none

Next Steps

  • David and Graham to develop an OLA/Several OLAs (based on W10) : Colleges CO's and Desktop CAB to agree KPI's and agree Roles and Responsibilities
  • David and Graham to develop an SLS (based on W10)
  • All documents to be run past Service team for feedback, Project Board review, Desktop CAB (No date set)

 

Future Milestones

Deliver Service Documentation approved by Team, Board and CAB 28-Feb-2020
Close Closure 13-Mar-2020

Project Sponsor Commentary

None.

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
a further delay in deliverable to be addressed by request of ITI director to prioritise this work
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Tony Weir
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Deployment of MAC Desktop to Labs
Code
DTP017
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Fraser Muir
Current Stage
Deliver
Status
In Progress
Project Classification
Grow
Start Date
07-May-2018
Planning Date
11-Jun-2018
Delivery Date
28-Feb-2019
Close Date
13-Mar-2020
Overall Priority
Normal
Category
Discretionary

Documentation