Deployment of MAC Desktop to Labs - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 GREEN 0.0 days 0.0 days 0.0
Content
Status
In Progress
Current Stage
Deliver
Start Date
Monday, 7 May 2018
Planning Date
Monday, 11 June 2018
Delivery Date
Thursday, 28 February 2019
Close Date
Friday, 13 March 2020
Project information
Project Code
DTP017
Programme
ITI - Desktop Services (DST)
Session
19/20
18/19
17/18
Organisational Unit
IS IT Infrastructure
Project Management Office (if relevant)
ISG PMO
Responsibility
IT Infrastructure
Project Category
Discretionary
Project Classification
Grow
Funding Source
ITI Core
Overall Priority
Normal
Student Impact
Project deliverables will be used by students