Report for Dec 2018

Report Date
December 2018

It was agreed with the Digital Transformation Board after the Digital Transformation review that this project would be closed.

A PICCL is being composed to support this and will be submitted to WIS w/e 18th Jan 2019.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Implement Integrated Identities
Code
DTI040
Programme
Digital Transformation - Integrated Identities (DTIP09)
Management Office
ISG PMO
Project Manager
Hilary Shand
Project Sponsor
Dave Berry
Current Stage
Close
Status
Withdrawn
Start Date
31-Oct-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal
Category
Discretionary