Report for December 2019

Report Date
December 2019

Achievements in Last Period

  • project started
  •  

Issues and Risks

  • n/a  

Next Steps

  • project brief and plan

 

Future Milestones

 

future milestones listed - the easiest way is a copy and paste from current milestones, with superfluous columns removed

30-Jan-2020 End of Planning
30-Jun-2020 Delivery
15-Jul-2020 Closure

 

GUIDE TO RAG STATUS : project_planning_-_guide_to_rag_status.docx

 

Project Sponsor Commentary / Approval

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Deployment of MDM Service
Code
DST201
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Graham Newton
Current Stage
Initiate
Status
Not Started
Project Classification
Transform
Start Date
25-Nov-2019
Planning Date
20-Jan-2020
Delivery Date
19-Jun-2020
Close Date
03-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation