Collections as Data - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 BLUE 0.0 days 0.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Tuesday, 18 December 2018
Planning Date
Friday, 8 February 2019
Delivery Date
Wednesday, 31 July 2019
Close Date
Friday, 9 August 2019
Project information
Project Code
DLIB002
Programme
Digital Transformation - Digital Library
Session
19/20
18/19
Organisational Unit
Library and University Collections
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Discretionary
Project Classification
Transform
Programme Priority
3
Overall Priority
Normal
Student Impact
Project deliverables will be used by students