w/c 17th June 2019

  • Technical Update 
    • Advised that Peter is working on the puppet code for Mongo dB this week (amongst other things) and Nigel is booked purely on this from Monday to get into test. 
  • User Acceptance Testing 
    • ​​​​​​​Still to complete tests on MongoDB - discussions on going to determine if latest data from edX can be uploaded to the Dev environment to commence checks 

​​​​​​​

Project Info

Project
Establishing Platform Data Store for DLAS
Code
DLAS012
Programme
Distance Learning at Scale (DLAS)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
03-Sep-2018
Planning Date
11-Jan-2019
Delivery Date
23-Aug-2019
Close Date
29-Nov-2019
Overall Priority
Higher
Category
Discretionary