Totara LMS Pilot - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2018 BLUE 135.0 days 135.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Friday, 9 December 2016
Close Date
Friday, 19 January 2018
Project information
Project Code
CSG011
Programme
CSG Portfolio Projects (OTHCSG)
Session
17/18
16/17
Organisational Unit
Corporate Services Group
Project Management Office (if relevant)
ISG PMO
Project Category
Discretionary
Funding Source
Sponsor funded
Programme Priority
2
Overall Priority
Normal