Report for February 2017
- Report Date
- February 2017
Achievements in Last Period
- Business partners have continued to undertake user testing of upgrades on new servers
- No testing issues reported (so far) on new infrastructure
Issues and Risks
- Milestones have been revised
- Database server has been as reported as being slow - under investigation
Next Steps
- UAT to be signed off
- Final preparations for deployment to be arranged
- Switchover to new infrastructure
Project status is AMBER because of revised milestones.
Milestones
| 17-Mar-2017 | Acceptance sign-off | Accept |
| 20-Apr-2017 | Delivery of new infrastructure | Deliver |
| 28-Apr-2017 | Deployment sign-off | Deliver |
| 12-May-2017 | Project closure | Close |
- Approved budget
- 23.0 days
- Activity this month
- 0.1 days
- Activity this year
- 17.6 days
- Activity to date
- 17.6 days
- Estimate to complete current year
- 5.4 days
- Estimate to complete future years
- 0.0 days