Report for December 2016

Report Date
December 2016

Achievements in Last Period

  • Replacement servers built and delivered by ITI Enterprise
  • New servers configured by Dev Tech according to business requirements
  • Build stage signed off

Issues and Risks

  • None reported

Next Steps

  • Vendors on site to install software upgrades and test these
  • Business partners to undertake user testing of upgrades on new servers
  • Discussions with business partners  and Production Management about deployment

Milestones

02-Feb-2017 Acceptance sign-off
22-Feb-2017 Deployment sign-off
17-Mar-2017 Project closure
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
23.0 days
Activity this month
6.5 days
Activity this year
11.8 days
Activity to date
11.8 days
Estimate to complete current year
11.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Sport & Exercise Replacement Servers
Code
CSG010
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Jim Aitken
Current Stage
Close
Status
Closed
Start Date
14-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Jun-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation