Report for October 2016

Report Date
October 2016

Achievements in Last Period

  • Project planning complete
  • Resources assigned & estimates prepared
  • Project brief approved by WIS & stakeholders

Issues and Risks

  • None reported

Next Steps

  • Undertake system analysis on Sport & Exercise infrastructure
  • Discussions with vendors about compatabilities & dates for deployment, etc.

Milestones

08-Nov-2016     Systems Analysis sign-off 
15-Dec-2016 Build sign-off
02-Feb-2017 Acceptance sign-off
22-Feb-2017 Deployment sign-off
17-Mar-2017 Project closure
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
23.0 days
Activity this month
2.4 days
Activity this year
3.5 days
Activity to date
3.5 days
Estimate to complete current year
19.5 days

Project Info

Project
Sport & Exercise Replacement Servers
Code
CSG010
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Jim Aitken
Current Stage
Close
Status
Closed
Start Date
14-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Jun-2017