Report for October 2016
- Report Date
- October 2016
Achievements in Last Period
- Project planning complete
- Resources assigned & estimates prepared
- Project brief approved by WIS & stakeholders
Issues and Risks
- None reported
Next Steps
- Undertake system analysis on Sport & Exercise infrastructure
- Discussions with vendors about compatabilities & dates for deployment, etc.
Milestones
| 08-Nov-2016 | Systems Analysis sign-off |
| 15-Dec-2016 | Build sign-off |
| 02-Feb-2017 | Acceptance sign-off |
| 22-Feb-2017 | Deployment sign-off |
| 17-Mar-2017 | Project closure |
- Approved budget
- 23.0 days
- Activity this month
- 2.4 days
- Activity this year
- 3.5 days
- Activity to date
- 3.5 days
- Estimate to complete current year
- 19.5 days