Report for June 2017

Report Date
June 2017

Achievements in Last Period

  • Project closed

Issues and Risks

Next Steps

 

Milestones

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
23.0 days
Activity this month
0.5 days
Activity this year
24.5 days
Activity to date
24.5 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Sport & Exercise Replacement Servers
Code
CSG010
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Jim Aitken
Current Stage
Close
Status
Closed
Start Date
14-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Jun-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation