Report for September 2016

Report Date
September 2016

Achievements in Last Period

  • Project given approval by business and IS Apps management
  • Initial discussions with business users
  • Project website set up and project brief started

Issues and Risks

  • None reported

Next Steps

  • Complete project planning & estimates
  • Submit project brief for approval

 

Milestones

14-Oct-2016 Planning sign off Plan
03-Mar-2017 Project delivery sign off Deliver
31-Mar-2017 Project closure Close
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
30.0 days
Activity this month
1.1 days
Activity this year
1.1 days
Activity to date
1.1 days
Estimate to complete current year
28.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Sport & Exercise Replacement Servers
Code
CSG010
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Jim Aitken
Current Stage
Close
Status
Closed
Start Date
14-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Jun-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary